It is the necessary infrastructure for the subsequent demolition of the A-8 highway overpass in that Bilbao district, a “complex” project, the implementation of which as a whole will take about nine and a half years.
Euskaraz irakurri: Errekaldeko says about proiektua aztertzen hasi dira
The Provincial Council of Bizkaia has started preliminary analyzes to “properly prepare”, a “complex ” project whose implementation as a whole will take about nine and a half years.
At the plenary session of the General Assemblies of Biscay in Gernika, the regional delegate for economic and territorial development, Imanol Pradalesat the request of the political groups in the Chamber of EH Bildu and PP
From the opposition groups, the representative of EH Bildu Raul Mendez and that of the PP Eduardo Andrade they have called for this project to be given “the same priority” as others.
According to Méndez, “with the adoption of the general urban development plan for Bilbao, there are no excuses” not to take it. Andrade, for his part, has criticized the fact that there have been “too many years of unfulfilled promises” and that the demolition of the viaduct “should be a priority”.
In his speech, followed by some Rekalde residents at the Casa de Juntas, Pradales explained that once the Bilbao City Council approved its General Urban Development Plan (PGOU) in the Provincial Council, “we have already started analyzing the geotechnical, environmental, urban and functional information that allows us to identify the critical points we need to provide the construction project” of the variant.
Six months prior analysis
As indicated, this task will be performed for six months and then the construction project
Pradales has emphasized that the construction of the variant and the subsequent demolition of the viaduct is a “complex” project that will take a long time to complete due to its “large size”, significant effects on the A-8 highway and on urban planning and environmental problems, as a tunnel has to be built.
He explained that for the elaboration of the construction project of the variant it is necessary to carry out some previous studies, it is necessary to prepare, contract and execute the bidding document for the construction project, which implies 48 months of work.
Subsequently, the bypass must be constructed and the viaduct demolished, with tender procedures, tendering and execution of works that 68 months extra work. All in all, they suppose116 months of constant and permanent work”, as indicated.
(function(d, s, id) {
var js, fjs = d.getElementsByTagName(s)[0];
if (d.getElementById(id)) return;
js = d.createElement(s); js.id = id;
js.src = “//connect.facebook.net/es_ES/sdk.js#xfbml=1&version=v2.8”;
fjs.parentNode.insertBefore(js, fjs);
}(document, ‘script’, ‘facebook-jssdk’));
Source: EITB

I’m Wayne Wickman, a professional journalist and author for Today Times Live. My specialty is covering global news and current events, offering readers a unique perspective on the world’s most pressing issues. I’m passionate about storytelling and helping people stay informed on the goings-on of our planet.