The Royal Majorca You already have permission to finish reforming the They are Moix, where the athletics track was removed and the stands were covered, among other actions. The Urbanism Management of the Àrea Model de Ciutat, Habitatge Digne and Sustainability has finally granted the license, with which the vermilion club will now be able to complete a project with a cost of 13,504,605 euros, as reported by the ‘Diario de Mallorca’.
The works of the first phase consist of the construction of a new stand in the lower part of the sun standwith a new tendency to bring spectators closer to just 8.5 meters from the pitch.
The second phase of the stadium’s remodeling, pending the granting of a building permit, consists of the remodeling of Northern Goala performance that will carry throughout time.
In the summer of 2023 the covered grandstand will be faced and in January 2024 the South Goal, which will complete the works. The project also plans to build a residence for youth players.
Source: La Verdad

I am Shawn Partain, a journalist and content creator working for the Today Times Live. I specialize in sports journalism, writing articles that cover major sporting events and news stories. With a passion for storytelling and an eye for detail, I strive to be accurate and insightful in my work.