The Outward that manages the Valencia City Council at NOU MESTALLA revealed that the material implementation project is 17% higher, 34 million, which finally indicates that disbursement, after repairing general costs, industry and tax benefits, will grow nearly 50 million euroswithout counting the rehabilitation of the structure or the chairs.
Approved by pare carrying out this study To find out what endorsement he asks the club if the works will stop again, as he did between February 2009 and January 10 of this 2025, as he left to do to finish the installation.
Made by Vielca Ingenieros, the audit, where the EFE had access, said the stadium cost, including the formed part, would reach 291.89 million euro to 341.46 million euros.
The study states that “it can be considered meets high quality requests Thanks to the prescribed brands, the constructive solutions adopted and the integration of modern facilities. “In that sense, Valencia contributed a letter from Uefa describing the main project with category 4, “The maximum of this organism.”
On the other hand, in terms of risks, it also features “It’s hard to get” The meaning of some planes, both architecture and facilities. Also that this is defined as “barely” issues such as chairs or “detailed solutions” of the athletics track although the project is included that it is part of a posterior or parallel stage “.
Warning the audit that the information transferred “is not allowed A detailed review To issue an opinion about the possibility of breaking the established deadlines ”.
The report also explains that both primary and execution projects are studied but is specified that in the second case a “Initial Edition” And it establishes that in order to finish the works it will need 17% more than the last budget contributed by Valencia suggests, representing 34.4 million euros. In the corresponding tax, the cost of the stadium will increase some 50 million euros.
Included in that figure One million for markers, Tornos and photovoltaic plates that do not include the club but not the cost of more than seventy thousand chairs or any rehabilitation work that needs to be done with the work already built.
The study confirms the 70,044 viewers’ capacity But it emphasizes that the club speaks of a “gross capacity” that can be reduced depending on the type of party or the demands of creature repair, but also featured that it can rise because there are some areas with no chairs where they are located.
About the request it can be compatible with installing a Athletics track He explained that the Valencia project focuses on a mobile platform “which fills the low stand” and thus creates ample space for a regulation track according to the International Federation.
The office in charge of the auditing ensures that there is a room to do it but does not enter the cost it may think. “The architectural solutionThe structure and installation for the platform, as indicated in the memory of the document reviewed, will be part of another project, so the cost of the same.
Regarding the project -set, office Fenwick Iribarren Arquitecs, reviewing its career and remembering that they are responsible for other stages of high places as some of Catar or Spain World Cups and Valladolid.
“Understand that signatures and mediated with companies In drafting the project they are professionals of the highest qualifications, as established in the December 20, 2005 agreement, ”he concluded.
Source: La Verdad