The speed of remodeling works Spotify Camp Nou It is on a very good track, better than expected. The demolition of the third tier of the stadium has been fully completed and work is starting to condition the first and second tiers with the aim of enjoying the stadium’s matches again. FC Barcelona in one year, in November 2024.
The time of execution of works is one of the great priorities of FC Barcelonabecause the Barça club wants to commemorate the 125th anniversary of the entity with the reopening of Spotify Camp Nouand that is one of the main reasons for choosing a Turkish company Limak as a builder. From Limak They have a commitment to all their projects to always finish on time and not go over budget, as they have done so far, as stated Haldun Firat Köktürkgeneral director of Limak Constructionat a briefing held at the company’s offices in Istanbul.
“Spotify Camp Nou is a project to take our first step in Europe. We needed a year to complete the contract with Barcelona. The discussions were not only financial because we had to convince them that we would finish the works on time and on time. budget,” he said. Köktürkwhich shows great confidence in meeting the planned schedule to change the Spotify Camp Nou and expressing his great enthusiasm for being able to carry out a task of such enormous importance as the Barça stadium.
In its part, Resit Yildizproject manager of Limak Investmentsalso clarified that the big priority is to finish the project on time and assured that “if you open the stadium a few weeks earlier, the income for our client will also increase and it will be beneficial for all parties.”
In this scenario and as a result of the good work of Limak For now, the Turkish company will receive a bonus of close to one million euros for advancing the deadlines for the demolition of the third tier of the Spotify Camp Nou. In the contract between Limak and the FC Barcelona Some bonuses are contemplated for certain milestones for weeks in advance, although there are also payouts if Limak not complying with the stipulations.
By November 2024, 65% of the work will be done
Joan Sentellesdirector of operations at Espai Barça, explained that the speed of works on Spotify Camp Nou is progressing without any setbacks and that by November 2024, the date on which the team must return to play in the Barça fiefdom, the first and second stands will be completely finished, as well as part of the parking lots, 50% of The VIP seats and the new Museum are now operational. The 360º circular screens on the second tier will also be ready.
The structure of the third stand and the VIP rings will also be completed, but there are still no seats, and the wiring will be raised to the roof of the stadium but the plates that cover the fans are still missing. The cover will be completed in summer 2025, where there will also be 90% capacity in the VIP rings. During this phase of the works, the Spotify Camp Nou store will open.
“The forecast is that by August 2026 the stadium will have no more works,” he said. Sentelles, which also noted that the locations will be 104,600 “although there may be fluctuations.” The new Spotify Camp Nou It’s shaping up and so far so good. In a year the ball should roll again.
Source: La Verdad